Thursday 1st February 2018

Now that we are putting the finishing touches on two of our contemporary lodges our focus moves towards updating the website. Please bear with us while we remove legacy text and images from the site which relate to West Pitt Farm Holidays in particular any reference to cottages.


Information relating to Oak & Beech Lodges such as pricing, availability, description and pictures are correct.


As the lodges are completed more detailed pictures will be added to the site.


Thanks


Seb & Angela


 

Posted in Luxury Lodges by .
Tags:

May update

May update

Friday 26th May 2017

Both lodges 1 & 2 are progressing nicely, first fix electrics and plumbing are complete and they have been plasterboarded.  The wetroom suites have arrived and will be installed once the tiling is complete. The kitchens are in storage waiting for the windows and doors to be fitted, they are being delivery on June 2nd. The larch cladding and decking are being worked on now.


Lodges 3 & 4 are in the process of being insulated ready for first fix electrics and plumbing.  The roofs have been finished.


All of the patio walls are being faced with local stone and are looking great.


 



 

Posted in Luxury Lodges by Seb Parker.
Tags:

Construction update

Construction update

Saturday 29th April 2017

Since our last update there has been huge progress with the construction of our luxury lodges.


Lodges 1 & 2 have been roofed and the first fix electrics and water are well underway.  Larch cladding and decking is on order with the doors and windows due towards the end of May.


All drainage will be complete next week so we can seed and plant up the ground down to the lake.


 

Posted in Luxury Lodges by Seb Parker.
Tags:

Construction update

Construction update

Monday 20th February 2017

Construction of our Luxury Holiday Lodges started in early November, after 3 months the groundworks are virtually complete with all four Lodges now out of the ground.


The frames should be erected in the next 6 - 8 weeks

Posted in Luxury Lodges by Seb Parker.